Project Requirements
Contract to complete all final finishing works to roads and footpaths.
To include :
- kerb replacements
- full gully builds
- setting iron works
- block paving roads
- tarmac removal and laying to footpaths and roads
- ramp formations
- drainage including drive acos
- lampost build out
What We Delivered
As seen in the photos, our men provide a very high standard of finishing.
Over 1050 m2 of block paving completed on this site.
various areas of tarmac laid on roads and footpaths approximatley 1200 m2
Fully insured and CHAS accredited
All machinery is provided by Advanced Paving and construction ltd